Natalie Creek Project Updates
The Kostner ave arch culvert, pedestrian bridge and detention basins were completed in the fall of 2019.
What’s next: Spring 2020
The work on the Kilbourn arch culvert should be completed by the end of March. The contractor will repave the work area once the asphalt plants open in mid/late April.
Work on the Kolmar arch culvert will begin in early April 2020 followed by the Kenton and Kilpatrick arch culverts in the summer/fall of 2020